| Farab
International
FZE along
with the
parent
company is
currently
engaged in
implementation
of the
following
Hydro
Power
Plants in
Iran. |
| |
| Delivered Projects |
|
| |
| Projects
Under
Execution
|
| |
| New
Awarded
Projects
|
|
|
| |
|
| |
|
|
|
|
 |
General
Information |
|
| Masjed-e-solyman (MES) dam and hydroelectric Power
Plant with a capacity of 1000 MW is located about 25 kilometers
north-east of the city of
Masjed-e-Soleyman in
Khuzestan province on
Karun
River.
|
 |
Dam Specifications |
|
| Type of dam : |
Rockfill with central clay core |
| Height of dam: |
177 m |
| Crest length: |
480m |
| Crest width |
15 m |
| Type of spillway: |
Gated spillway
weir with aerated chute and stilling basin |
| Volume of reservoir: |
288 million m³ |
 |
Power House Specifications |
|
| Type of
power
house: |
Underground |
| Capacity: |
1000 MW(4 units of 250
MW
each) |
| Capacity after extension |
2000 MW |
| Average
annual
power
generation: |
3700 million KWh |
| Client: |
Iran Water & Power Resources
Dev.Co. |
| Consultant: |
Association of Moshanir, Nippon Koei and Lahmeyer
Int. |
 |
Specifications of
the Main
Equipment |
|
|
Turbine : |
4 x 254 MW ,187.5 rpm vertical francis turbines 700 tons each. |
| Generator
busducts: |
4 units insulated phase busducts 15.75 KV and 11.5 Ka |
| Butterfly
valves: |
4 units with inner outlet diameter of 5.3m and approximate weight of 272 tons each |
| Governors: |
4 units digital type with digital backup governors |
| Transformers |
13 x 94 MVA single
phase with an approx weight of 100 tons each |
| Flap gates |
4 units
with steel lining and approx dimension of 8x5.9m operating with two hydraulic servomotors (approx weight of 37 tons each) and approx .water pressure of 60.8 m |
| Generators |
4x250MW,187.5rpm,15.75kv, vertical shaft with approx .weight of 950 tons each |
| SF6 switchgear |
2x400 KV tree
phase
circuits |
|
|
|
|
|
|
|
 |
General Information |
|
|
The extension of Shahid Abbaspour Power Plant with
the capacity of 1000 MW is located 50 Kilometers
north - east of the city of Masjed-e-Soleyman in Khuzestan province
on karun River. Capacity of the existing power plant is 1000 MW
. After completion of erection of
extension, the capacity of the power
plant will be 2000 MW.
|
 |
Dam Specifications |
|
| Type of dam : |
Concrete
arch dam |
| Height of dam: |
203 m |
| Crest length: |
383m |
| Foundation width: |
36.5m |
| Area of reservoir: |
55km² |
| Type of spillway: |
Gated chute
spillway |
| Volume of reservoir: |
3000 million
cubic meters |
 |
Power
House
Specifications |
|
| Type of
power house: |
Underground |
| Capacity: |
1000 MW(4 units of 250
MW each) |
| Average
annual power generation: |
4000 million KWh |
| Client: |
Khuzestan Water & Power Authority |
| Consultant: |
Association of Moshanir and
Lahmeyer Int. |
 |
Specifications of
the
Main
Equipment |
|
| Turbines: |
4 x 245 MW vertical francis turbines with an approx weight of 650 tons each. |
| Generators: |
4 x 250 MW Generators with an approx. weight of 1200 tons each |
| Butterfly
valves: |
4 butterfly
valves
with an approx. weight of 2000 tons each. |
| Governors: |
4 units digital type with digital backup governor
|
| Transformers: |
13 single
phase step-up
transformers100
Mva,15.75/400 KV with an approx. weight of
110 tons each |
| Hydraulic steel structure: |
Gates ,penstocks ,steel
linings, trashracks and related equipment. |
| Crane: |
Two powerhouse cavern overhead
cranes
with a total lifting capacity of 2 X 320 tons.
|
|
|
|
|
 |
General
Information |
|
|
Karkheh dam and hydroelectric power plant with a capacity of 400 MW is located 20
kilometers
north-west of the city of
Andimeshk in
Khuzestan province built on karkheh river. |
 |
Dam Specification
|
|
|
Type of dam : |
Earthfill with clay core |
| Height of dam: |
127 m from foundation |
| Crest length: |
3030 m |
| Crest width |
12 m |
| Foundation width: |
1100 m |
| Type of spillway: |
Ogee type |
| Volume of reservoir: |
7800 million m³ |
 |
Power House Specifications |
|
|
Type of power house: |
Surface type |
| Capacity: |
400 MW(3 units of 133.3 MW) |
| Average Annual Power Generation: |
934 million KWH |
| Client: |
Iran Water & Power
Resources Dev. Co. |
| Consultant: |
Mahab Ghods consulting
engineers |
 |
Specifications of
Main
Equipment |
|
|
Turbine : |
3 vertical francis turbines with an approx weight of 560 tons each. |
| Generator: |
3 Generators with an approx. weight of 755 tons each |
| Butterfly valve: |
3 butterfly
valves with an approx. weight of 233 tons each. |
| Governors: |
3 units digital type with digital backup governor.
|
| Transformers: |
3
three phase step-up
transformers 160 MVA,
with an approx. weight of 147 tons each. |
| Hydraulic steel structure: |
Stoplog
gates of draft tube |
| Crane: |
Two power house main
cranes each with a lifting capacity of 225 tons |
|
|
|
|
|
 |
General Information |
|
| Location : |
Chaharmahal-e-Bakhtiary province, Shahr-e-kord, chelgered by the Kouhrang No. 2 Diversion Tunnel |
| Client : |
Iran Water & Power Resources Dev. Co. |
| Consultant : |
Moshanir Co. |
|
 |
POWER HOUSE SPECIFICATION |
|
| Type of Power House : |
Surface |
| Capacity : |
39.3 MW (3 units of 13.1 MW) |
| Average Annual Power Generation : |
128 million KWh |
|
 |
SPECIFICATION OF MAIN EQUIPMENT |
|
| Turbines : |
3 Units Vertical Francis Turbines, with an approx. weight of 30 tons each |
| Speed : |
500 rpm |
| Transformers : |
2 Units Three phase Step-up 25 MVA, with an approx. weight of 36 tons each |
| Generators : |
3 units Generators, with an approx. weight of 50 tons each |
|
|
|
|
 |
General
Information |
|
| Karun 3
Dam and Hydroelectric Power
Plant with a capacity of 2000 MW
is located about 28 kilometers east of the city of Izeh in Khuzestan
province on Karun
river. |
 |
Dam Specifications |
|
| Type of dam : |
Concrete
arch dam |
| Height of dam: |
191 m |
| Crest length: |
388m |
| Foundation width: |
29 m |
| Area of reservoir: |
46 km² |
| Volume of reservoir: |
2750 million
cubic meters |
 |
Power House Specifications |
|
| Type of
power house: |
Underground |
| Capacity: |
2000 MW(8 units of 250
MW each) |
| Average
annual power generation: |
4137 million KWh |
| Client: |
Iran Water & Power Resources
Dev.Co. |
| Consultant: |
Association of Mahab Ghods and
Acres Int. |
 |
Specifications of
the
Main
Equipment |
|
| Turbine : |
8 x 254 MW ,187.5 rpm vertical francis turbines with approx weight of 8x700 tons each. |
| Generator: |
8 x 250 MW vertical shafts with approx. weight of 8x 890 tons |
| Butterfly
valves: |
8 units of butterfly valves
with an approx weight of 8x275 tons |
| Governors: |
8 units digital type with digital backup governors |
 |
Hydraulic steel structure |
|
| 1-Dam: |
|
| Service spillway: |
4 radial and 4 sliding gate with hoist servomotors(1145 tons) ,steel lining(3200 tons) |
| Orifice spillway: |
4
radial and 4 sliding gate with Hoist servomotors(1145 tons) ,steel lining (3200 tons)
|
| Flow
compensation outlet: |
3
hollow cone valves(70 tons) 2 sliding and 2 bulkhead gates (100 tons), one gantry crane for bulkhead gate (80 tons) one under-hung crane (25 tons) |
| 2-Intake:
|
| Deck: |
24 stoplogs(600 tons)
48 trashracks(460 tons),
one gantry crane(53 tons) |
| Gate gallery: |
one bulkhead and 4 sliding gates with hoist servomotors(300 tons) one overhead crane (130 tons) |
| 3-Tailrace: |
12 stoplogs(360 tons) one gantry crane (53 tons) |
| 4-Power house: |
2
overhead cranes( each 2x150 tons ) one overhead crane for inlet valve (100 tons)
penstock steel liner (2500 tons) |
|
|
|
|
|
 |
General Information |
|
| Location : |
Khuzestan Province - 166 Kilometers South-West of Shahrekord City - on Karun river |
| Client : |
Iran Water & Power Resources Dev. Co. |
| Consultant : |
Mahab Ghods Co. |
|
 |
POWER HOUSE SPECIFICATION |
|
| Type of Power House : |
Surface |
| Capacity : |
1000 MW (4 units of 250 MW) |
| Average Annual Power Generation : |
2107 million KWh |
|
 |
SPECIFICATION OF MAIN EQUIPMENT |
|
| Turbines : |
4 Units Vertical Francis Turbines, with an approx. weight of 700 tons each |
| Butterfly Valves : |
187.5 rpm |
| Governors : |
4 Units Generator, with an approx. weight of 980 tons each |
| Generators : |
13 Units Single Phase Step-Up 100MVA (1 unit is spare), with an approx. weight of 100 tons each |
|
|
|
 |
General Information
|
|
|
Location: |
Underground power house |
| Client : |
Iran Water & Power Resources Dev. Co. |
| Consultant: |
Khuzestan Province - 25 Kilometers North-East of Masjed Soleyman City - on Karun river |
 |
POWER HOUSE SPECIFICATION
|
|
| Type of Power House : |
Underground |
| Capacity |
1000 MW (4 units of 250 MW) |
| Average Annual Power Generation : |
3700 million KWh |
 |
SPECIFICATION OF MAIN EQUIPMENT |
|
| Turbines |
4 x 254 mw, 187.5 RPM Vertical Francis, 700 tons each |
| Generator Busducts |
4 units Insulated Phase Busducts, 15.75 KV and 11.5 KA |
| Butterfly Valves |
4 units, with inner outlet diameters of 5.3 m and approx. weight of 272 tons each |
| Governors |
4 units digital type with digital back up Governors |
| Transformers |
13 x 94 MVA single phase with an approx. weight of 100 tons each |
| Flap Gates : |
4 units Gates with Steel Lining and approx. dimension of 8 x 5.9 m operating with two Hydraulic Servomotors (approx. weight of 37 tons each) and approx. water pressure of 60.8m |
| Generators : |
4x250 MW, 187.5 rpm, 15.75 KV, Vertical shaft with an approx. weight of 950 tons each |
| SF6 Switchgears : |
2 x 400 KV three phase circuits XLPE 400KV Cable |
| |
|
|
|
 |
General Information |
|
| General Information |
Tehran province, Jajrood, Latian Dam Rd., on Sohanak Tunnel |
| Client : |
Iran Water & Power Resources Dev. Co. |
| Consultant : |
Lar Consultant Engineers Co. |
|
 |
POWER HOUSE SPECIFICATION |
|
| Type of Power House : |
Underground |
| Capacity : |
47 MW (2 units of 23.5 MW) |
|
 |
SPECIFICATION OF MAIN EQUIPMENT |
|
| Turbines : |
2 Units Vertical Francis Turbines |
| Speed : |
750 rpm |
| Transformers : |
2 Units tree phase Step-up 27 MVA |
| Generators : |
2 units Generators |
| |
|
|
|
 |
General Information
|
|
| Location: |
Khuzestan Province - 25 Kilometers North of Shooshtar City - on Karun river |
| Client : |
Iran Water & Power Resources Dev. Co. |
| Consultant : |
Mahab Ghods Co. |
|
 |
POWER HOUSE SPECIFICATION
|
|
| Type of Power House : |
Surface |
| Capacity : |
1000 MW (4 units of 250 MW) |
| Average Annual Power Generation : |
4500 million KWh |
|
 |
SPECIFICATION OF MAIN EQUIPMENT
|
|
| Turbines : |
4 x 254 MW, 187.5 RPM Vertical Francis, 530 tons each |
| Transformers : |
13 single phase step-up 105 MVA (1 unit is spare), with an approx. weight of 100 tons each |
| Generators : |
4 Unit Generators, with an approx. weight of 880 tons each |
| |
|
|
|
 |
General Information |
|
| Location: |
Mazandaran province, 125 Kilometers north of Tehran city on Chalus river. |
| Client : |
Iran Water & Power Resources Dev. Co. |
| Consultant : |
Association of Moshanir & Colenco & Sakoo |
|
 |
POWER HOUSE SPECIFICATION |
|
| Type of Power House : |
Underground (Pump Storage) |
| Capacity : |
1000 MW (4 units of 250 MW) |
|
 |
SPECIFICATION OF MAIN EQUIPMENT |
|
Turbines : |
4 Units vertical Francis Pump, Turbines with capacity of 260 MW in Turbine Situation and 235 MW in Pump Situation each one |
| Speed : |
500 rpm |
| Transformers : |
13 Unit single phase step-up, 100 MVA (1 unit is spare) |
| Generators : |
4 Unit Generators, Motors with capacity of 300 MVA in Generator situation and 290 MVA in Motor Situation |
|
|
|
|
 |
General Information |
|
| Location: |
Mazandaran province, 125 Kilometers north of Tehran city on Chalus river. |
| Client : |
Iran Water & Power Resources Dev. Co. |
| Consultant : |
Association of Moshanir & Colenco & Sakoo |
|
 |
POWER HOUSE SPECIFICATION |
|
| Type of Power House : |
Underground (Pump Storage) |
| Capacity : |
1000 MW (4 units of 250 MW) |
|
 |
SPECIFICATION OF MAIN EQUIPMENT |
|
| Turbines : |
4 Units vertical Francis Pump, Turbines with capacity of 260 MW in Turbine Situation and 235 MW in Pump Situation each one |
| Speed : |
500 rpm |
| Transformers : |
13 Unit single phase step-up, 100 MVA (1 unit is spare) |
| Generators : |
4 Unit Generators, Motors with capacity of 300 MVA in Generator situation and 290 MVA in Motor Situation |
|
|
|
|
 |
General Information |
|
| Location: |
Ilam province - 30 km northwest of Dareshahr city - on Seymareh river |
| Client : |
Iran Water & Power Resources Dev. Co. |
| Consultant : |
Mahab Ghods Co.
|
|
 |
POWER HOUSE SPECIFICATION |
|
| Type of Power House : |
Surface
|
| Capacity : |
480 MW (3 units of 160 MW)
|
| Average Annual Power Generation : |
843.8 million KWh
|
|
 |
SPECIFICATION OF MAIN EQUIPMENT |
|
| Turbines : |
3 Units Vertical Francis Turbines with approx. weight of 470 tons each
|
| Speed : |
187.5 rpm
|
| Transformers : |
3 units three phase step-up, 190 MVA, with an approx. weight of 165 tons each
|
| Generators : |
3 Units Generators, with an approx. weight of 800 tons each
|
|